Anticipated before-and-after images of this remarkable project may not be available at this time, as construction has yet to commence. The design phase spanned approximately 15 months, followed by a 7-month permit acquisition period along with Value Engineering to more align with budgetary wants and needs. Construction, projected to last between 15 to 18 months, is pending. However, I am pleased to share the design and concept board shared with clients during the programming phase, serving as our guiding blueprint. For further insights on this project and my experiences navigating its intricate design process for the renovation of a century-old building, visit the “Insights” page.